The new installation ball mill needs a period of adjustment. During the adjustment, the first addition of the steel ball quantity account for 80% of ball mill maximizing ball capacity. The proportion of steel ball added is determined by the size of steel ball. The ball capacity is different for different ball mill models, for example, for a MQG15003000 type ball mill, its maximum ball capacity is 9.5-10 ton.
The reasons why the steel ball quantity only adds 80% in the period of ball mill adjustment are that the gearwheel and pinion of ball mill need meshing after the installation of ball mill, and the treatment capacity increases gradually. After the ball mill operating continuously and normally for two or three days, check the gearing mesh of gearwheel and pinion and when all is normal open the ball mill manhole cover for the second addition of the left 20% steel ball.
When the ball mill is in normal operation, add each steel ball group by 3:4:3. Note: the addition of the little ball is just for the first ball adding match, as when the ball mill is in normal operation, the reasonable frictions between steel ball and steel ball, steel
ball and ore, steel ball and ball mill liner plate will increase the abrasion and make the large ball smaller, the medium ball into little ball.
So in normal condition, the ball mill needs no more addition. Only when the monomer dissociation of valuable mineral granularity does not happen and the fineness of or mill is under the flotation demands, the little ball can be added. The steel ball in the ball mill wears down gradually in operation. The reasonable ball adding compensating for the abrasion aims to keep filling ratio and reasonable match of the ball, and maintain the stale operation of the ball mill.
The weight of the steel ball added is determined by the steel ball quality, as the steel ball quality is a determinant of ore additive amount. It is best to adopt the new type wear resistance steel ball. The best steel ball addition method is calculating the ore quantity per ton (that is to say, adding 0.8kg ore per ton). Generally, disposing one ton ore needs 1kg-1.2kg steel ball. For different types of ball mill, the size comparison of steel ball is different.
Cone crusher manufacturer : http://www.hxjq-crushers.com/27.htm
hammer crusher : http://www.hxjq-crushers.com/26.htm

There are lodges that aim to cater their guests with the best service available..
Read

housemaid agencies in dubai, agencies for maids in dubai, agency for maids in dubai.
Read

There are many other places that you could stay, but if you want the best experience, you should always make it a point to stay at professional fishing lodges. These lodges can give you everything a fisherman could ever need..
Read

We all are aware of the fact that the planet earth is facing the fury of global warming. Industries create lots of pollution and all the harmful gases are released into the atmosphere affecting our mother earth..
Read

DLF Maiden Heights located at Rajapura, Bangalore. DLF Maiden Heights offers luxurious 2BHK and 3BHK apartments with world class amenities..
Read

Global ADay.org Project Photograph Your Lives Global ADay.org Project Photograph Your Lives.
Read

Traitors always Pay for Their Treachery in the End Traitors always Pay for Their Treachery in the End.
Read

How to Improve the Capability of Sand Maker How to Improve the Capability of Sand Maker.
Read

Obvious Features Make Ball Mill a Great Assistant Obvious Features Make Ball Mill a Great Assistant.
Read

Brief Introduction about Sand Washing Machine Brief Introduction about Sand Washing Machine.
Read